Canada Just Burned $20 BILLION… And They’re Celebrating

14m 59s2,337 palavras344 segmentsEnglish

TRANSCRIÇÃO COMPLETA

0:00

Have you ever wondered why an

0:01

announcement of a pipeline completion

0:03

approval could just go from right at the

0:07

top today's biggest headline to nearly a

0:10

page 12? Well, it's usually the data

0:13

behind it. See, we need to ask

0:15

ourselves, how much does a government

0:16

delay cost? Not in theory, not in

0:19

politics, but in real dollars today.

0:23

Because on Friday, Ottawa stood up and

0:26

told Canadians something very

0:28

interesting about the Nbridge pipeline.

0:31

Now, one, it's a natural gas pipeline

0:33

and they have approved that pipeline. It

0:36

is a 4 billion pipeline and they want

0:39

you to believe that that's somehow some

0:42

type of show of leadership despite this

0:44

pipeline being ready to go in 2022. They

0:48

want to show you that it's somehow

0:49

progress for Mark Carney and his Liberal

0:51

government, that they've somehow

0:52

established momentum. But what if I told

0:55

you that that same project used to cost

0:57

hundreds of millions, if not a billion

1:00

less than it will cost to do today when

1:03

the shovels hit the ground in July. And

1:06

all that's changed was time. No redesign

1:09

of the project, no expansion, no new

1:12

scope to the whole thing. just simply

1:14

the fact that it took from 2022 to 2026

1:18

to get approved. And today, we're going

1:21

to not let them get away with that.

1:23

We're going to prove something that

1:24

should honestly make every single one of

1:26

you stop and think about what this

1:27

Liberal government is doing to our

1:29

economy. Canada is just too slow to

1:33

build. And Canada is making itself far

1:36

poorer by choice. So, let's tap into the

1:39

truth.

1:41

Welcome to Bakes on Things.

1:47

>> Welcome back to Tap to Maple here on

1:49

your Sunday edition. Happy Sunday,

1:50

everybody. Grab six, seven coffees. I

1:53

don't care what it is. Let's do this

1:54

today together. Here's the headline.

1:57

Don't forget to like, subscribe, and

1:58

join the conversation. By the way, the

2:00

federal government just approved the

2:02

Sunrise expansion. Yay. Let's launch

2:05

fireworks. a natural gas pipeline

2:07

project in British Columbia led by

2:09

Enbridge tied into the West Coast system

2:12

and directly feeding LG export growth

2:14

through projects like wood fiber LNG and

2:18

the messaging around all of that energy

2:21

superpower jobs created security for the

2:24

country opportunity knocks all great

2:27

words the same words in fact that we

2:29

heard in 2022 when the project was first

2:32

put up for approval but here's what

2:35

they're also not telling you this

2:37

project didn't just show up last week,

2:39

did it? It didn't start here in 2026. It

2:42

didn't even start in 2025. In fact, this

2:45

project has been in planning,

2:47

engineering, consultation, and more

2:49

since actually before it was put up for

2:52

approval. So, that's 2020 and 2021,

2:55

meaning by industry standards, this

2:58

thing's been ready to go for a long

3:00

time. They don't want you asking

3:02

questions about that or pointing that

3:03

out. Hence down to page three. Now let's

3:06

see why it went even further down. Well,

3:08

because it's not conceptual. It wasn't a

3:10

theoretical project. It was ready to go.

3:13

And yet here we are just giving it now

3:16

the approval it deserves in 2026

3:20

post a giant surge of inflation. So,

3:24

when we think about the construction,

3:26

which is scheduled to begin here in the

3:28

summer of 2026, again, there's a reason

3:31

they're not launching fireworks, because

3:33

here's the question. If it was ready

3:35

years ago, why are we only approving

3:37

this project now with no major changes

3:41

to the project since four years ago? And

3:43

more importantly, what did that delay

3:46

cost us? Or what it is is it about to

3:49

cost us. So, let's walk through all of

3:52

this in good time so that everybody

3:55

understands this, including the

3:56

Liberati, because this is where

3:58

Canadians get misled very often by this

4:01

Liberal government, and it's time to

4:03

hear the truth. When you hear that this

4:05

is a $4 billion project, you assume

4:08

that's just what it costs to produce.

4:11

But that's not how this infrastructure

4:13

that are that is like this works. Costs

4:17

evolve over time. There is time value to

4:20

money. And in Canada, they don't just

4:22

evolve, they explode because of our

4:25

inflation rates over the last half

4:27

decade. Because between 2022 and today,

4:31

construction costs have been rising

4:33

roughly 5% per year, then another 5%,

4:39

then 4% in 2024, then 3% in 2025. And

4:43

while that's declining over time, it

4:45

compounds on itself. So that is about an

4:49

18% increase in what it costs today to

4:52

build this pipeline versus if we had

4:54

approved it in 2022. So let's rewind. If

4:57

Sunrise had been approved in 2022 and

5:01

that summer shovels went in the ground,

5:03

it would likely have cost us 3.3 billion

5:06

to 3.5 billion in the end. Instead, we

5:10

are going to pay well over 4 billion for

5:12

this project to actually be built. Now,

5:15

that is roughly $500 million to

5:19

potentially 700 million to potentially

5:22

an extra billion gone. No new pipeline

5:25

yet, no added capacity, no upgrades,

5:30

none of that stuff is costing us more.

5:33

It's just that the base project itself,

5:36

the waiting has cost us more. That's

5:39

where that price tag comes in. So, let

5:41

me make that real for you right now.

5:44

Let's let's take a look at some of the

5:45

real picture associated with those

5:48

calculations. $700 million is hospitals.

5:52

It's infrastructure. It's tax relief.

5:55

All burned, burned, burned, burned, gone

5:58

on the bonfire. Hope you went camping

6:00

because and can roast marshmallows cuz

6:02

you burned all the money because we

6:04

couldn't do this in less time. That's

6:07

the whole reason. Now, if Sunrise was

6:10

the only example of our mistakes made

6:13

here, then, you know, maybe you let this

6:15

one pass, maybe you say, "Okay, well,

6:18

stuff happens. Things got behind. It's a

6:20

construction project after all. I've

6:22

done renovations and they've gotten

6:23

behind." But it's not the first time.

6:26

It's not the only time. And it's a list

6:28

of many. So, if we zoom out to things

6:30

like Trans Mountain expansion, which

6:32

started at 5.4 billion, do you want to

6:35

know what that should be now? If Trans

6:37

Mountain expansion is built and

6:39

completed at this point, over 34

6:42

billion, from just over five billion to

6:45

over 34 billion. And that's not entirely

6:48

inflation, of course. That's not even

6:51

complexity itself that's causing that.

6:53

That's a $28 billion failure to execute

6:57

on the project. Coastal Gas Link, it had

7:00

an original price tag of $6.6

7:04

billion. What do you think that price

7:07

tag is now? Take a guess.

7:11

14.5 billion.

7:13

14.5

7:15

billion. Another $7.9 billion increase.

7:21

Wood fiber LNG the one that this is

7:23

meant to feed even here tied directly to

7:27

Sunrise. Enbridge originally had

7:30

expected that that particular project to

7:34

cost $1.5 billion dollar

7:38

now closer to $2.9 billion. All of this

7:45

extra spending

7:47

almost not almost double in that case

7:50

not related to the project's pieces at

7:53

all. It's related to the waiting. So

7:55

stop and think about this. Just these

7:58

projects alone, when added together,

8:01

have over $38 billion in cost increases

8:06

related simply to time. Not a rounding

8:10

error, not some sort of coincidence.

8:13

That's a system. It's our broken system.

8:16

And the delay costs you. That's $ 38

8:19

billion on your back now. Because had we

8:23

approved these things four years

8:24

earlier, the $ 38 billion would not have

8:27

existed. So, here's where this gets even

8:29

more dangerous. Because people hear

8:31

those numbers and they think, "Well,

8:33

yeah, things get more expensive over

8:35

time. It's just the government. It's

8:37

just what the government does. Oh, it's

8:39

the government. Don't worry about it."

8:41

No, no, no, no, no, no. This is why your

8:43

taxes go up. This is why your fuel taxes

8:45

go up. This is why carbon taxes are

8:47

introduced. None of that is what's

8:49

happening. What's happening is something

8:50

I call the delay tax. In fact, that's

8:53

exactly what this is. It works like

8:56

this. Every single year you delay one of

DESBLOQUEAR MAIS

Registe-se gratuitamente para aceder a funcionalidades premium

VISUALIZADOR INTERATIVO

Assista ao vídeo com legendas sincronizadas, sobreposição ajustável e controlo total da reprodução.

REGISTE-SE GRATUITAMENTE PARA DESBLOQUEAR

RESUMO DE IA

Obtenha um resumo instantâneo gerado por IA do conteúdo do vídeo, pontos-chave e conclusões.

REGISTE-SE GRATUITAMENTE PARA DESBLOQUEAR

TRADUZIR

Traduza a transcrição para mais de 100 idiomas com um clique. Baixe em qualquer formato.

REGISTE-SE GRATUITAMENTE PARA DESBLOQUEAR

MAPA MENTAL

Visualize a transcrição como um mapa mental interativo. Entenda a estrutura rapidamente.

REGISTE-SE GRATUITAMENTE PARA DESBLOQUEAR

CONVERSAR COM A TRANSCRIÇÃO

Faça perguntas sobre o conteúdo do vídeo. Obtenha respostas com tecnologia de IA diretamente da transcrição.

REGISTE-SE GRATUITAMENTE PARA DESBLOQUEAR

APROVEITE MAIS DE SUAS TRANSCRIÇÕES

Inscreva-se gratuitamente e desbloqueie o visualizador interativo, resumos de IA, traduções, mapas mentais e muito mais. Não é necessário cartão de crédito.